top of page
AIM Past Project
Geovert completed an integrity survey of the 60m high Double Brick lined Chimney Stack working with GHD Consultants.
Project Overview
View Project
View Project
View Project
QAL Chimney Stacks
Projects
The Chimney stack was accessed by aide, ascending from the ground up using Hilti Mechanical Shear Set Bolts. Cover meters were used to map reinforcing and plot locations for core samples. Once core samples were taken holes were entered with a Bore Scope to survey strata and lead chimney lining seals. Schmitt Hammer and Impact Echo tests were used. On completion of testing holes were repaired. As part of the work a structural integrity survey of the existing Access Ladders and Platforms was under taken.
Project Solution
bottom of page